Multiple Choice

What is the purpose of comparing actual progress and costs to the baseline?

Comparing actual progress and costs to the baseline focuses on variance analysis: using the approved plan as a benchmark to see where the project is deviating. By spotting variances between what was planned and what happened, you learn whether you’re over budget or behind schedule, and you gain the signals needed to take corrective actions to bring the project back in line with the plan. This monitoring and adjustment cycle is the primary purpose of tracking against the baseline in cost control. Other options aren’t the main purpose because they describe possible outcomes that can occur later (termination, lessons learned, new approvals) rather than the immediate decision-making trigger that comes from detecting variances and correcting course.

Comparing actual progress and costs to the baseline focuses on variance analysis: using the approved plan as a benchmark to see where the project is deviating. By spotting variances between what was planned and what happened, you learn whether you’re over budget or behind schedule, and you gain the signals needed to take corrective actions to bring the project back in line with the plan. This monitoring and adjustment cycle is the primary purpose of tracking against the baseline in cost control.

Other options aren’t the main purpose because they describe possible outcomes that can occur later (termination, lessons learned, new approvals) rather than the immediate decision-making trigger that comes from detecting variances and correcting course.